|
|
Project AchievementsNew Power Plant
Replacement of Offshore Electrical EquipmentThis Project will provide the replacement of various offshore electrical equipment, which has been utilized for more than 30 years and being superannuated, on Flow Stations (Y-1, Y-2, Y-3 & Y4). Pump Platform, Ratawi Gathering Station, Living Quartar, Offshore Control Platform Ex-loading Dock and valves Station. New Switchgear Rooms will be installed set each platform to accommodate all electrical systems.
Installation of Gas Supply Facilities from OffshoreThis project will provide 12' Fuel Gas submarine pipeline from gas lift platform to onshore, Onshore gas receiving facilities, and Onshore gas line to Khafji Separators area in order to cover the shortage of Fuel Gas to be utilized for New Power Plant and other facilities at Onshore.
Expansion of Water Treatment Facilities, Phase 2New Water Treatment Facilities were constructed with wastewater handing capacity of 3,000 gpm plus standby capacity of 1,000 gpm. A new switchgear house building will be constructed in compliance with the security and safety directive (SSD) regulation a water treatment facilities.
RE-Construction of Business & Community Districts
The new facilities to replace existing KJO facilities are:
Community Support Facilities
New Power GeneratorA new 30-megawatt generator was installed successfully to enhance the current three generators and increase the total production capacity of KJO to 120 megawatt. Moreover, additional eight DBs were installed to supply power to the future projects. The operating system of the current generators and the current control system in the control room were replaced by modern operating and control systems.
Renovation of Water Treatment Facilities Phase-2The work is goning in full swing to renovate and construct new Water Treatment Facilities of larger capacity (3000 GPM) to separate oil from water. This project will increase the capacity of the Station in line with environment and safety requirements.
40KV Submarine Cable and GISThe project includes engineering, procurement and construction of a new 40KV power transmission system. The major facilities involved are a 42 km submarine cable (40 kV, 20 MVA, three (3) cores) inclusive of a build-in -fiber optic cables, two (2) 40 kv Substations comprising of Gas insulated Switchgear (GIS) one each at onshore and offshore and an offshore platform, namely Utility Platform (UTP).
Construction of No. 2 Gas Lift StationThis project will provide four Gas turbine compressors with conditioning skid. TEG gas dehydration system and related facilities in order to supply enough capacity of gas lift for all planned gas lift wells and onshore fuel gas.
Modification of Offshore Control systemThis project intends to replace the tie-worm offshore SCADA system with DCS for the Gathering platform and Flow Stations. DCS will communicate with PMCR and HCR Onshore. This existing field instrumentation will be modernized by replacing numeric instruments by electronic instruments and by refurbishing other instrumentation.
Installation of Security Monitoring System, This system includes:
* Security perimeter fence a accordance with SSD-1
AGOC Home OwnershipHome ownership is a major Program Land lot area is 1.5 sq. km. (1km X 1.5km) at Al- Khafji. The Program involved design, Tender, Construction and commissioning of Infrastructure and other Community Support Facilities 850 Land lots with a total area of 1.5 sq. kms (1 km. X 1.5Km.).
Industrial ProjectsOnshore Projects:
* Renovation of Loading Facilities Offshore Project:
* Installation of New Flow Station Utilities Projects:
* Construction of Sea Water Desalination Unit
Constructing Two New Gas Lift StationsStation 1 & Station 2:New Gas Plant was recently constructed within Khafji Joints Operations facilities and currently under commissioning. The new facility will collect all separated gas from Khafji Reservoir from both onshore and offshore. The objects of this new gas plant are the followings:
2- Minimize Flaring by collecting all flared gas at offshore and send it to new onshore gas plant. 3- Recover NGL and export it to both shareholders.
|
|